There is a common
theme when delivering a project; it requires finesse to obtain all the relevant
information to ensure the information is accurate. However, there has to be a
distinct separation on the information being delivered, in particular, the
separation between, if it is a plan or a schedule. A plan is where the approach
is mapped out to deliver versus the schedule which covers the tasks and
dates.
Depending on the
size of the program it is best to use Microsoft project to build plans as
opposed to using Excel. When reporting high level milestones for governance
purposes Excel is an invaluable tool, but to use it solely during the delivery
of a project is recipe for failure. If an Audit is conducted it can be looked
upon as a violation of SDLC practices.
Strategic plans can
deliver business value; the default project plan can be used as a starting
point, but some things cannot be automated or standardised. These kinds of
tools so only be used for reference purposes, and not as shortcuts to doing the
thinking about what is really needed to execute successfully. It is a fine
balance between reinventing the wheel each time and working with your own data.
Plan out the success
criteria with stakeholders and craft out the high level milestones that task will
roll-up to deliver the vision. The tasks must be prescriptive and should be
done in short form tweet like entries. Declarative entries should be used to
perform and validate. Words like Secure, Verify, Validate, Obtain, Draft, Approve and
Distribute should be commonplace throughout the plan.
Project plans which
require rework have the following characteristics;
- Task durations are greater than 10 or 15 days. When would it be known that a 60-day task is late? On the 61st day it is too late to affect any kind of change. Tasks that have a long duration require subtask items to allow for follow-up and remediation.
- Keep the schedule up to date, if all stakeholders agree to the approach and its reflected in the plan, then it should be used to manage day to day deliverables.. Tasks that are past due with no percentage completed is a red flag. Find out if teams have skipped tasks or decided certain deliverables have been deemed out of scope.
- Tasks are not prescriptive enough to convey work deliverable. It doesn’t have to be overly elaborate but at least include enough information to make it reusable
Unfortunately, Project Managers tend to get assessed on the existence of
artefacts but not necessarily on the quality of products that get
produced. It is time to start looking at how project plans connect
to success criteria and how the details drive the intended result.
Start performing self-checks and peer reviews and include stakeholders in
the process. Share plans with them and ask them to comment on dates
and resource availability. That is a great way to get buy-in and
learn from others.
Comments
Post a Comment